November 1998
. . .I have not been on
site as much as I would have wished. But progress has been swift.
During July and August - which this year were extraordinarily wet -
some of the subterranean work was done. The drainage was installed,
and one of the basements excavated. Unfortunately nothing of any
interest was discovered; but the process coincided with the
so-called 'slapping' which is a curious term for penetrating the
wall. Some wall, in this case. To get the services into the cellar,
a hole had to be created through ten feet of solid rock.
. . .In normal circumstances, this
would be no easy task. But it turned out to be far from normal.
Hammer, chisel, pick and flashlight were presented to the stones,
but what we thought was rubble - indeed WAS rubble, on the surface -
became bedrock. The wall was not just constructed on rock; in the
mid-section, the wall WAS rock. So an ingenious material which
expands (slowly, fortunately) had to be drilled into the surface
every few inches, and left overnight to grow and split the unbroken
bedrock of which the middle of the wall consisted. The process of
getting a pipe for services from inside to out took three weeks.
. . .For gentle relief from the
soul-destroying task of breaking through from cellar to outside
world, the builders began to excavate the floor of the 'guard-room',
the small chamber just inside the main door into the castle. The
going suddently became unexpectedly easy. Hammers in hand, they
discovered a void under a layer of concrete, concealing a small
chamber in the thickness of the wall. Iain Thornber, local historian
well-known to MacInneses, went up on site immediately, and returned
with a resident archaeologist the following day. He describes it
thus:
"The chamber is about seven foot
deep, 8 foot long and about four feet wide tapering at the west end
below the trap door. The ground is remarkable bare and we think we
found bedrock. It is surprisingly 'empty' and from the marks on the
walls (which still show signs of vegetation) I would guess it too
was excavated or more likely cleaned out by the Ross squad"
(the people involved in the Victorian restoration).
. . ."The
interesting thing is that the walls show signs of having been coated
with a lime mortar. There are several blocks of limestone showing
some good examples of gryphea and other fossils. Three large
mica-schist flagstones form the roof of the chamber. There is some
dampness on the internal wall (which was obviously built later),
indeed it is almost a steady trickle caused perhaps by the fact that
the roof has recently been opened rather than a leakage from
anywhere else. It will be interesting to take some levels to
establish where it lies in relation to a) the outside ground level
and b) the floor level of the vaulted cellars. At a cursory glance I
am inclined to think the East End of the chamber was bricked up at a
later stage and may well continue."
. . .We will certainly retain access to
this exciting new find, probably
through a trap-door in the guardroom floor. I shall inform the
authorities in due course.
. . .Meanwhile a service duct was being
cut into the interior wall, to get the pipes etc. from basement
level to the top storey. Hard work, but not complicated. The tin
roof came off, and concrete padstones - beds for the load-bearing
joists - were constructed in the wall-head. Scaffolding clothed the
outside of the building, to parapet level - and since then, higher
still. Twelve inch steel joists were hoisted in, with a crane
working from the foot of the castle rock extending nearly 30 feet to
get to the foot of the walls, another 40 feet to the wall-heads, and
still more to give clearance to lower them into place.
. . .So the supports for the second
floor were in, and on them a wooden floor constructed. Then the
gables started rising above the parapet. The top two stories are
masonry outside, and wooden-framed inside. The wood goes up first,
so a strange apparition rose from the wall-heads: a kit house 40
feet in the air. We've never seen a Barratt home with such good
foundations, people joked (Barratt are a proprietary form of
speculative, rapid-build timber-framed house).
. . .Things have moved fast since. A
period of good weather in September meant the roof trusses went up
swiftly, and during October the sarking. The chimneys are built, and
the framework of the top stories is almost complete. Slating is the
next major development to be visible from outside.
. . .Meanwhile below little has
happened. Windows remain unfitted and the intermediate floor
unchaged. As the evenings draw in, Jane and I are poring over
electrical plans, and deciding where to put furniture and pondering
how a 6-foot long sofa will go up a narrow spiral stair (it won't).
. . .Second-hand baths and sinks must
be found and plumbing finalized. Several large trees - oak, larch
and Scots pine - were felled, taken into the estate yard and milled.
The planks are away to be seasoned, and then back to make floors,
doors, architraves and skirtings. The approach-road has been
resurfaced - not for the last time - to soak up some of the autumnal
mud.
. . .Things are going well, and each
visit reveals more of what we will shortly be living in. Some rooms
are small, but the views are sensational. The parapet-walk will be
the finest place for a sundowner in the western highlands.
. . .By the time of the next bulletin,
the windows should be in and the floors laid. Now that the rain can
be kept out, the process of domesticating the ancient stones begins.
|