KICKING HORSE CANYON PROJECT
June 2004 to present;
Project value: $730 million
www.kickinghorsecanyon.ca

Project Summary: The Kicking Horse
Canyon Project, being undertaken with federal funding
assistance, involves upgrading approximately 26 kilometres of
the Trans Canada Highway from the junction of Highway 95 in
Golden to the western boundary of Yoho National Park to a modern
four lane standard, including bridge replacements.
The
project, which includes the construction of several new and
replacement bridges, is being undertaken in three phases, the
latter of which is to be delivered under a DBFO arrangement
which will ultimately cover the operation and maintenance of all
improvements undertaken in the project. Phase 1 of the project,
involving the construction of a new Yoho (5 Mile) Bridge and
approaches, is nearing completion. Phase 2, the replacement of
Park (10-Mile) Bridge is under construction with completion
expected in 2008, while Phase 3 is in the early planning stages
and will address improvements to the balance of the corridor.
Activities: As part of the owner’s
engineer team, JS&A provides advice and services in stakeholder
relations and public consultation to the Ministry of
Transportation. This includes strategic management and support
to the Ministry’s project management team and PAB in:
-
Public consultation and
communications strategy development
-
Defining the respective roles
and responsibilities of the Ministry and the
Design-Build-Finance-Operate
(DBFO) contractor with respect to communications and
stakeholder relations
-
Open houses and information
sessions (including notification and advertising)
-
Facilitating communications
with key stakeholders, particularly with a view to
minimizing and mitigating construction impacts
-
Municipal relations and
Council presentations
-
Website content development
-
Media relations support
-
Project and issues management
Results: Local, provincial, national
and international awareness for the Kicking Horse Canyon Project
is high. Input is being solicited and applied in the design
process, and an ongoing dialogue has been developed with the
establishment of a liaison committee representing a
cross-section of the local community and other key stakeholders. |