FINAL ASSEMBLY
MISCELLANEOUS
Even with all the previous talk about preparation and
painting, it still leaves a question about how much painting to
do before assembling the cabin onto the main frame vs. painting
after the panels and pieces have been screwed and riveted in
place. In general, I'm choosing to do as much painting as
practical before the parts are installed as this allows me to
easily check the coverage / quality and to get paint on the
various faying edges. More importantly, all the aluminum
preparation (i.e. alodine and primer) is done while the panels
are easily handled as individual pieces. My general idea is to
topcoat wherever possible and to leave the exterior of the cabin
sheeting in primer till after all riveting has been done.
Hopefully, once the entire cabin has been riveted together then I
can apply a bit of primer over the rivets and the outside will
then require a sanding of all the primer and just the final
topcoat(s).
There are a lot of smaller pieces, such as interior panels and
the shroud components, whose painting sequence is not really
important other than to get all the pieces done before final bolt-on
assembly. Where appropriate, I wet-riveted these pieces with
primer into larger sub-assemblies before actually painting them.
One exception was the side panels that go between the seats and
the door sills; these parts were painted before riveting due to
potential difficulties getting into the deep recesses with the
spray gun.

What happens when I have too much time waiting
for other painted parts to dry/cure
Wherever possible, smaller assemblies were pre-riveted
together and various holes have already been drilled/cut and
verified. I've chosen to paint the inside of the panels in the
cabin area with a single coat of white so as to improve the
visibility in the area under/behind the seats when performing
maintenance. Because this area is "hidden", it allowed
me to practice my painting technique. I'm not sure how others
have done their assembly sequence, but I thought I'd share my
sequence and reasoning.
I chose to try do as much work on the cabin area as possible
without the bubble or boom attached. Leaving the bubble off made
for very easy access to various areas when doing things such as
the wiring. Once the boom is installed it makes it much more
difficult to move the craft around and it also makes for a lot of
extra walking around or sliding underneath it. There really is no
need to attach the boom until work begins on the tail rotor
driveshaft. I also kept the ship on the casters as long as
possible ... this made it harder to do some of the engine stuff
as it was closer to the ground but it also made it much easier to
move the ship around and the lower height was very convenient
when working on the transmission and fuel tanks.
- Main Frame - The main frame was prepped and then painted.
The rotating joints on the pedal assembly and cyclic
pivot were first sealed by wrapping a single layer of .020"
safety wire around them and I had some plastic plugs
inserted into the various tapped holes. Since I had the
frame lightly sand blasted, the nutplates were not
installed before paint and they were subsequently primed
& riveted in place. Tubeseal was introduced into the
frame and then it was rotated several times. Considering
the complexity of the structure, I'm not sure that all
areas received a coating, but hopefully most of them did.

- Controls - Before installing any sheeting on the frame,
the throttle rod and cyclic / collective system should be
prepped, painted and installed. In addition to the
exterior surfaces, I also chose to coat the interior
surfaces of all open tubes. On the various areas where
there is sliding or rotating surfaces, I chose to coat
these areas with Perma-Slik G. Final preparation and
installation of the cyclic sticks has been deferred until
after the seat cushions have been installed so that the
required height based on my seat cushions and cyclic
grips can be determined. Note
that once the rear side sheeting is in place, it becomes much
more difficult to install the control system through the
firewall area and virtually impossible to do so once the
engine is installed.
Note: Once the controls and collective trim spring have
been installed, there will be considerable downwards
force on the forward end of the collectives / throttles.
Any rotation of the throttles while the collectives are
down can quickly wear the paint off the contact point on
the throttles. Perhaps UHMW tape on the contacting
surfaces will delay the wearing off of the paint.

- Bottom Sheet - It looked kind of weird, but the bottom
panel was primed and the area behind the middle rib was
given a white topcoat and the area ahead of the front rib
was given a grey interior colour topcoat. Note that both
sides of the "lips" also require the colour
coat.
- Bottom Ribs (Front, Center and Sides) - The center rib
was left with just a full primer coat on the front side
and a light topcoat of white on the backside. Likewise
for the two small side ribs. Because of my heat ducting,
there are some difficult to reach rivets on the bottom of
the front rib and bottom edge of the heat duct. The front
rib was initially only done in primer so the sequence
became: rivet front rib to belly pan (the important joint),
rivet heat duct to rib and then topcoat the front of the
rib. Note that there is just a bit of the area inside of
the front rib at the outside edges that may be visible
after final assembly; I painted this area with my
interior grey colour. The
three bottom ribs were riveted to the bottom sheet before
any of these were re-attached to the main frame which
made for easier access without having to contort around
frame members.

- Firewall Ribs (4) - The top and bottom ribs were fully
topcoated before assembly in order to reduce the masking
and difficulty in painting them after assembly. Since
there are several rivets in the side ribs that are
installed after initial assembly but are visible, I was
planning to initially only basecoat the outside of the
side ribs. Once the cabin is ready for final topcoat, the
side ribs would be exposed in the mask and receive their
topcoat which would be relatively easy as there is a
natural separation line. Like
a lot of plans, this one managaed to change. I was going
to pre-paint just the flanges, but by the time I did this
there was enough overspray and weird looking effect that
I finally just put on a full topcoat. After some
experimentation, it looks like I can put a topcoat on
just the flush rivets without it looking too obvious
since there is a natural line around the rivets. I was
very careful when installing rivets on these topcoated
parts to use riveting tape on them to avoid marring the
surface and any need to repaint the whole part. The safer
alternative (from a paint perspective) would have been to
use pulled rivets but they aren't as strong.
Note that the throttle torque tube should be installed
before the bottom firewall rib is installed. Although it
could be installed or removed / installed at a later
time, this would require the slot in the firewall rib to
be enlarged.
- Door Sills - I chose to pre-paint these with my interior
grey colour as I figured this would save a lot of masking
that would be required if they were painted after
riveting. The only large masking job that will be
required after the main assembly will be for painting the
exterior of the main hull and the entire interior should
already be completely painted by then.
- Side Sheeting - The large rear side panels received an
interior coat of white and the exterior was left in
primer. The front chin panels got an interior coat of
grey since a bit of the front of them is visible after
assembly. The rear door sill
was riveted to the sides, but the front door sill was
deferred until after the floorboard was installed.

After riveting these pieces and before installing the
floorboard, I chose to finalize the locations and drill
the holes for my pitot tube and belly COM antenna.
Although I have some access to this area after the
floorboard is mounted (i.e. enough to tighten the nuts
& connections), it's a lot easier to drill and deburr
the holes when one has total access to both sides.
Although I do have a heated pitot tube available, it will
require a special mount to be fabricated so I chose to go
with the CHR-supplied one initially just to keep the
project rolling along. My final location was about 2-1/2"
behind the vertical part of the front rib and I added an
inside doubler plate that spans most of this.
The antenna location is a compromise since there is not
enough length in the belly pan to provide the ideal
clearances for a bent-whip COM antenna and the tranponder
antenna. I chose to mount the COM antenna about 22"
behind the front lip of the belly pan which is about
ideal for forward and sideways radiation. It is slightly
off center so that the coax will clear the heater SCEET
tube on the inside. The transponder antenna is mounted
very far back on the belly pan (just under 3"
forward of the trailing edge) and slightly offset to the
opposite side from the COM antenna. Both antennas have a
doubler plate but I still have a bit of concern about
whether there is enough rigidity in the belly pan for the
COM antenna ... I may have to eventually add a piece of
side-to-side angle to spread the load.
- Floorboard, Floor Bins and Switch Console - All riveting
was done on these sub-assemblies before installation as
was all the painting. Before
installing the floorboard, I first installed the SCEET
tubing for the cabin heat duct and also drilled the
floorboard for the pitot tube and the belly mount antenna
pass throughs which will be installed later on. Although
parts of the switch console are riveted to the
floorboard, the actual switch panel was not installed at
this time since it will be pre-wired as much as possible
and installed once all painting is complete. Due to
maximizing the size of my floor bins, these bins had to
be placed in position before the floorboard and then
fastened to it during assembly since they cannot be slid
in (or removed) at a later time. Note that due to my
wider than normal floorboard, the front door sills were
not riveted to the side sheeting until after the
floorboard was installed.

Once the switch panel and wiring have been installed,
it's impossible to remove the floorboard without a major
effort. It is possible to put a small bead of RTV sealant
or rubber tape between the frame tubes and the floorboard
such that any "drumming" would be prevented and/or
absorbed by the RTV. Of course, I figured this out and
discussed this with another builder after my floorboard
became non-removeable (at least without a lot
of work). One should also be careful of any of the
centerline screws that may be covered by wires later on.
In addition to making sure there are no burrs that could
cut into the wires, one might want to add some blue
thread locker to these bolts so they won't loosen under
vibration.
- Door Frames(P-channel), corner pieces, eyebrow panels and
bubble capstrip - These pieces were all worked on
together so that I could do a final tweak on the eyebrow
panels before riveting all these pieces in place. The
bubble had to be installed then removed but I believe it
was the right way to do it since there was some
definitely some final changes to the eyebrow panels that
I felt could only be done once the side panels had been
riveted and locked in place. Once again I learned to
curse the eyebrow panels and the difficulty in getting a
perfect fit. The door frames and corner pieces were pre-painted
so as to get coverage on the ends and to avoid the need
to mask for overspray while the eyebrow panels and bubble
capstrip were topcoated on the inside and left in primer
on the outside. The fact
that several of the CHR drilled rivet holes in the P-channel
were right against the center of the angle made the
riveting much more difficult and hopefully these will not
cause future problems.
One issue that I ran into is that the forward-most rivet
hole in the eyebrow / P-channel joint is such that the
tail of the rivet will actually contact the bubble and I
had a concern that in addition to forcing the joint away
from the bubble, it would also dig into it and create a
stress riser. Before removing the bubble for riveting, I
used a sharpie through the rivet hole to mark the bubble
where this contact would be. Since this is on the white
doubler material on the bubble, I chose to carefully
grind a relief in the doubler. When riveting this hole, I
chose to use a minimal length rivet and to purposely
slightly over buck it to lower the profile. During bubble
installation, I will also add a dot of RTV in this relief
to spread out the load and dampen any vibrations. Time
will tell whether this is still a sound joint.
The door frame corner pieces are extremely soft and their
holes were no longer in good shape after the various use
of clecos during fabrication. Because I'd dimpled these
for flush rivets, this helped somewhat but I also chose
to back up all rivets with rivet washers to get a
clamping action and hopefully prevent future working of
these rivets. There are a couple of difficult to buck
rivets on the lower doorsill but I eventually got them
all bucked with solid rivets by using a variety of
different bucking bars. I cheated on the corner trim
pieces and just used pulled rivets.
- Exterior Cabin Painting - In preparation for painting the
exterior of the cabin, I first used a small brush to put
a bit of primer on each of the rivet heads. Because I'm
using flush rivets, I've found that this extra primer
seems to allow for a better topcoat as it smooths out a
bit of the very sharp edge on the rivet head. The pre-primed
exterior panels were then sanded with maroon Scotch-Brite
after two riveting oopsies were first filled. Note that
there is one last chance before exterior paint to do a
little "massaging" of some of the panel edges.
I found that in a few areas around the door sills the
sheeting edges had slightly lifted due to the riveting
process. These were easily coerced back into place with
careful use of a hammer.
In order to try keep the bubble cap strip in it's final
position, I used black clecos (5/32") installed from
the inside in the screw holes; the outside two screw
holes had cap bolts installed to keep the edges of the
eyebrow panels flush during painting. Although the
exterior masking requirements are obvious, I chose to
also mask the interior side of all the seams since spray
paint seems to find the minutest hole to seep through.
- After the paint on the cabin had fully cured (about a
week), I took a close look at the firewall area and
looked at the various openings around the tubes and the
deeper flutes in the corners. I decided that there were
significant gaps that I wanted to seal and I used Fire
Barrier 1000 silicone sealant since I'd managed to find a
tube of it locally. I think that a good RTV (possibly
high temperature) would do an equally effective job.


At this point, I had to make a decision whether to proceed
with the engine installation or the cabin components. Although
some of the work is being done in parallel, my emphasis is on the
cabin. The reason for this is that the hangar I'm working in is
quite dusty due to composites work and I want to get the bubble
mounted before doing any of the wiring. I had planned to defer
the bubble mounting till very late in the process, but the only
thing that becomes really awkward with it installed is mounting
the instrument pod. Thus my next priority is to mount the
instrument pod and then the bubble. Even before the doors are
finalized and hung, I can install the firewall and hang sheets of
polyethylene over the door openings to try minimize dust entry.
- Before the engine and bubble are installed, it's easy to
tip the cabin back to work on the bottom of it. I made
sure that I'd done everything I wanted to do before
proceeding. Due to clearance issues, the pitot tube and
belly antenna mounting are deferred until after the ship
is on it's skids, but the short transponder antenna was
mounted at this time.
- At this point, I also added the "rubber"
molding around the front and back of the cabin where it
contacts the bubble. This was glued in place using 3M
8011 (black) weatherstrip adhesive which worked quite
well for me. I first put the molding in place dry and
placed some 1/4" painter's masking tape layed flush
alongside it. This allowed me to brush on the adhesive
without worrying about getting it where it wasn't wanted.
By waiting to remove the tape until after the molding was
installed, I was also able to remove with ease any excess
adhesive that squished out.
While I was working with the weatherstrip adhesive I also
glued the 1/16" rubber pads onto the top of the fuel
tank saddles. I found it easiest to first cut the
supplied sheet to the required width but leave each piece
longer than required by about 1/2" or so. After the
rubber strips had been glued in place and the adhesive
had cured overnight, it was then a simple mattter to trim
them to length using an X-Acto knife.

- I was originally planning on painting my instrument pod
with Stone
Creations (Black Granite) which would give it a dark
rough texture. This requires a clear topcoat to protect
it and after finding a satin clear that was compatible, I
made up several test strips. I wasn't happy with the
durability of the result so it was time to switch to
epoxy urethane. I wanted a darker colour to try stop some
reflection and I already had too much gray in the cabin
... black was okay but boring. So out with another colour
plus a low-gloss clear coat.

Definitely a perspective error ... this pod is
significantly smaller than than the CHR version
- Like many things releated to this project, the priority
has slightly shifted. Since I now have access to a
relatively clean hangar, I've decided to continue
installing various interior items, hang the engine and
then perform most of the wiring. The bubble will be
installed once the majority of the wiring in the console
pod and switch panel is complete. Although the bubble
could be installed at this time, it will make it slightly
more convenient to access various things when wiring the
instrument pod to have unobstructed access.
In preparation for hanging the engine, the firewall must
be installed first which will eliminate access from the
rear to the controls and other areas. I first finished as
much of the controls adjustment as I could and also
installed the cargo hook plug and LASAR® wiring harness.
Although it would have been easier to install some of the
other firewall penetrations at this time, I've deferred
these until the engine is in place so as to optimize
their location. However, I did add a strip of 1/4"
painter's masking tape to indicate where the bottom of
the frame tube is and thus avoid drilling penetrations in
areas that wouldn't work.

Firewall installed and ready for engine mounting
Hindsight: It actually would have been easier to
have routed the wires for the engine sensors at this time
just before installing the firewall. To access the
firewall penetrations from the front (i.e. firewall in
place) requires a long awkward reach while it would be
easier to do this from the rear. Either way will work,
it's just that one is much easier on the back. As far as
location goes, I chose to have these wires exit the cabin
in the lower firewall rib just to the right of the hook
bracket.
- With the firewall in place, the next task was to install
the engine. This was pretty straight forward and the only
glitch is that my caster system is quite low and wasn't
designed for the legs on an auto hoist which I had to use.
I had to temporarily remove the oil filter and one mag
cap to make the installation around the frame members
much easier. New conical bushings are also a bit of a
pain as they tend to try grab the bolt as it is being
installed and torqued.
At this point, my engine was basically bare. The
conversion for dry sump operation had already been
performed and all shroud building / fitting had been done.
However, the only shroud pieces attached were the bottom
two pieces (due to conical bushings), the #3 baffle and
the small part of #1 baffle ( I lifted the engine in from
the right or opposite side). Pretty well any more of the
shroud will interfere with the lifting / installing
operation and/or would have just gotten in the way. The
alternator, carb and exhaust system had also remained off
the engine since they really are not needed before this
and it was easier to keep the engine sealed without them.
I've also deferred sensor installation till after
everything has been aligned since these are just more
things that can get snagged or interfere with other tasks.
Note that if one is using anything other than an
AN816-4[D] straight fitting (which works fine) for the
oil pressure transducer, you should check the clearance
to the engine mount before
installing the engine. In the case of angled fittings,
they must be installed before engine installation unless
the builder wants to get some practice in removing and re-installing
the bolts and lifting the engine.

- With the engine in place, the next task was to try
install the transmission and drill / bolt the four pylon
struts. I'd tried this twice before and it caused me a
lot of grief ... this time was no different. The
transmission did not line up perfectly with the mounting
holes and I used a couple of old bolts ground to points
to act as drift pins. Eventually I still had to slightly
open up a couple of the holes. Since this is a bit of an
iterative process, I also used temporary bolts as they
need to be installed and removed quite a few times. The
next issue was with the pylon struts and it appears the
major source of problem is that one of the aft struts is
5/16" longer than the other one. In reality, it
would have been a lot simpler if it had been 1/4" shorter.
Part of the transmission installation process is
to determine if the engine needs any kind of shimming. I
chose to do this initial alignment with the fan/clutch
drum and the clutch shoes removed. This makes it very
obvious whether there is a mis-alignment since the lower
nut on the transmission input actually fits just into the
snout of the engine's crankshaft and is fully visible.
While I was doing this, I also took my clutch drum / fan
to the local propellor shop to have a static balance
performed on it ... I know it is out of round and assumed
that it would have significant balance issues. Hopefully
the static balance will be a good starting point until I
can perform a dynamic balance. Interestingly, it only
required one AN960-10L washer to achieve static balance.

Rear and side view ... the yellow lines are
graphically inserted to help show the forward tilt to the
engine at this point
I believe there are two main ways that have been used to
get the engine and transmission aligned:
1) Just install everything and torque it down till it
seems to fit.
2) Align the transmission to the frame using the pylon
rods and possibly some shims, then align the engine to
the transmission with shims and/or conical bushing
compression.
I'm choosing the second alternative since I believe it is
the proper way to do things. Although I've been told by
CHR that shims are not required and to just torque
everything down and adjust the conical bushing bolts, I
have a tough time doing this and knowing that there will
be a significant pre-load stress on various frame members.
I required .125" shims under the transmission right
side mounts and .063"-.080" under the rear
mount. The engine also required some shimming ... AN970-8
washers (0.109") under two of the mounts were too
much and I ended up using .063" shims.
This is one area that I may want to re-vist after the
ship is operational. Without the shim under the right
mount, the mast would be tilted in that direction which
should help to offset any translating tendency (tail
rotor drift). It will also interact with the resulting
rolling tendency.
- Note: The plug in the snout of the engine's crankshaft
that is used for a fixed pitch engine is prone to rusting
and not sealed from the atmosphere in the Safari
installation. In fact, water could actually collect here
if the craft is exposed to rain and it would be
impossible to spot this without pulling the transmission.
I put a heavy coat of Corrosion-X
on this area to try ward off any rusting.
- I sent an email to CHR about the pylon rod that was too
long and inquired whether they might have a different rod
that would meet the shorter length that I required. The
next morning I got a phone call indicating they had
already fabricated a new one for me and were just double
checking whether to finish it with the measurements I'd
sent or to leave off the ears on the upper end and allow
me to custom fit and weld it. Since I have a good TIG
welder on the field, I chose the latter and CHR managed
to get the parts to the courier by 11:00 AM that day for
express delivery. I sincerely appreciate their extremely
quick response to this matter and they should be
commended for it.
- Since I consider this one of the most important steps in
the whole build process, I spent a lot
of time trying to get the engine, transmission and pylon
support rods into perfect alignment before drilling the
top holes in the pylon rods and the spider on the mast
... more in the Controls
section. In fact, this step drove me crazy and I finally
realized that I couldn't get perfection but just the best
compromise. After temporarily installing and marking the
rods to verify they'd fit and how deeply, I took them off
and drilled the holes in the upper rod ends to 3/16"
while trying to make sure the holes were square to the
tabs. The rods were then re-installed, firmly clamped in
place and then each hole was through drilled into the
pylon. An AN3 bolt could also be installed at this point
to preserve alignment. The holes were then opened up with
a 7/32" drill followed by a D drill while coming in
halfway from each side for the various drilling
operations. The holes were then reamed to 1/4" for
their AN4 bolts (I'm actually using AN174 close tolerance
bolts ... they're a couple
of thousandths larger and a gentle tap in versus slide in).
Also note that the lower front bolts on the rods have nil
clearance to the firewall ... I can just
get a castle nut and a thin washer in there with two
regular washers on the head side.

Clamped and ready for drilling ... also note the
sheet to collect drill chips and keep them out of the
clutch / engine
- With the main shaft locked into position, I could finally
determine the actual length and finish fabrication of the
straight control rods that go from the cyclic bellcranks
to the swashplate. Although this is slightly jumping
ahead, it was done so the control rods and pylon rods
could be painted at the same time. The
pitch rod could also be installed and the slot in the top
firewall rib opened up to it's final size. The updated
rigging instructions call for having the swashplate level
laterally and 2-1/2" or more from the pylon to the
bottom of the swashplate spider. It also calls for the
swashplate to be level in the fore-aft plane, the lower
knuckle to be level or slightly angled up and the upper
knuckles to be at 18 degrees. This can be a pain to try
set the control rod lengths while everything is flopping
around so I came up with a simple plan. I used four short
equal length posts between the swashplate and spider to
hold everything in it's final position while I finished
fabricating the rods and adjusted everything. A bit of
trial and error produced posts that were 2.76" long.
I have a lathe to make these kinds of posts but
alternatively, four AN4-25 bolts would have been
relatively close and a reasonable starting point.

Rear and side view of spacer posts (yes, there's no safety wire or
nuts on pylon bolts ... this is pre-paint)
Update: I've received information from another
builder who tried this technique. He initially tried
posts that were 2.82" long but could not get the
full range of control motion that was required. He then
switched to 2.69" posts and obtained the required
amount of movement.
- With the pylon rods drilled and painted, the transmission
could be final bolted into place. The first step was to
bolt and safety wire the ring gear support and clutch
drum to the crankshaft (N.B.
don't forget to install the alternator belt).
With the transmission suspended for installation and all
tape residue removed from the clutch shoes, the shoes
were re-installed and held in place with band clamps (the
ones to be used for SCEET tubing). The transmission and
the pylon rods were then installed followed by the clutch
shields . Everything was double checked and then the
various cotter pins were installed (remember to include
the engine mount bolts). Finally ... a permanent install
of the drivetrain.

Left: Safety wire installed; Right: Clutch shoes
installed and band clamps holding them in position
Note that in the Rigging Manual it talks about aligning
the individual fan blades so they track at the same
height. I'm deferring this until I'm ready to run my
engine as this step requires one to rotate their engine
and I don't want to do that to a pickled engine.
- I'd left my alternator off the engine during
construction, except to check the belt clearance on the
shroud. The alternator was final installed at this point
and I found that it was easier to first install the
shroud's baffling above the #1 cylinder as the screws
holding the two parts together are difficult to access
with the alternator in place.
Note that I've provided the Lycoming torque
specifications in the Shop
section. These are the torques on the alternator pulley
nut where the belt just starts to slip and are a much
more reliable way of setting the tension than the classic
belt deflection method. Although I thought I had my belt
quite tight, I was surprised to find that it was only
about 3/4 as tight as the Lycoming method when I double
checked it. Since it's awkward to adjust once the shroud
and oil cooler are in place, it's best to just get it
right the first time.

The baffle above #2 cylinder was also installed
and then it was time to install the carb and various
engine sensors. The first step was to mount the carb
temperature sensor since it is on the back side and it is
impossible to remove the plug after the carb is mounted.
Upon opening the bag with the CHR-supplied carburetor
mounting bolts, I was surprised to find two AN5-11 and
two AN5H-10A bolts versus the packing list of four AN5-11
bolts ... obviously as a builder neophyte I hadn't
spotted this when I inventoried my kit. The -11 bolts
will probably just work with my MA4-5 carb if I use thin
washers (not supplied with the kit) but first I have to
place yet another order for bolts and washers.
While I was looking at the carb, I decided to trial fit
the mixture plate that was included in the kit. Even
though my kit was clearly ordered as being for an O-360,
the mixture plate (and construction prints) are for a MA4
carb as found on an O-320 ... one more item to be
designed / fabricated / tested. I'm not sure how this
relates to the required moment arm, especially since the
mixture arm on the MA4-5 carb actually rotates downwards
as it moves. There is also a difference in the throttle
arms on the two carbs and the Safari instructions
regarding which hole to use are meaningless. Needless to
say, this was a very frustrating build session when all I
wanted to do was simply bolt the carb into place ... what
a waste of time and effort to try identify and correct
more factory oversights.

Note the mixture arm at front of the MA4-5
carburetor
- I temporarily remounted my oil cooler so I could get the
actual lengths for the hoses. I chose to use braided
lines on these and needed to get the correct length and
obtain supplies. After measuring for them, the oil cooler
was removed and I went on to finish some interior and
control items. I chose to run the oil cooler lines
between the cylinders and the intake runners as this
affords them the most protection and the cleanest install.
However, I think one needs to be somewhat conscious of
the heat from the cylinders and to also think ahead about
where the starter, alternator and MP lines / wires will
be routed. They can all fit inside the runners, but it
does get fairly crowded, especially if one is also
running a ground strap through here.

- The cyclic control lock was finished at this point. By
making sure that the stick was exactly parallel to the
mast, it makes the final adjustment of the control rods
much easier. I also had to considerably enlarge the slot
in the top firewall rib to allow for the full range of
motion for the pitch rod.

- The various engine and transmission sensors were
installed at this time in preparation for wiring the
craft. It might have been a bit easier to first check and
plan for these while the engine was still horizontal in
the crate but the only one that might be required before
installing the engine would be an angled oil pressure
fitting.

Note safety wire hole drilled in transmission
temperature sensor
- I wasted a lot of time trying to get the stock CHR
exhaust system to fit. Although it is not required at
this point, I was planning on having it ceramic coated
and needed to verify that it fit properly before sending
it away. Instead of just a fit and verify process, this
has turned into a cut, splice, bend, reinforce and weld
process that wasted a lot of time and effort due to very
poor quality and an unuseable fit of the factory parts.
Certainly not the bolt-on fit that I was expecting when I
ordered this very expensive item.
- With the exhaust "can" in it's final position,
I re-assembled the shroud and installed the oil cooler
and heat collector duct. That allowed me to see how well
(not very) that the SCEET tube connecting the two of them
would fit. I also decided to modify the oil cooler duct
and #2 baffle to try improve the airflow to #2 and #4
cylinders. Lower retension straps for the heat collector
were also fabricated.

- I'm sort of jumping around at this point and finishing
off a lot of odds and ends. The primary focus is in
getting the wiring completed but there are plenty of
other small tasks to distract me. One of them is to
fabricate some "boots" for where the three
control rods exit the firewall ... it's been bothering me
to have these three large holes just being left wide open.
Until the boots are completed and installed, I can't do
the final installation / adjusting of the control rods
nor can I do the final install of the shroud front since
I need access to the firewall.
- The switch panel and solenoid board are now installed and
wired together. Because the mixture & cabin heat
controls are in the panel and I used adel clamps under
the solenoid board, they've also been installed but the
back end won't be terminated for a bit. Having the
control cables under the floor board makes for a clean
installation and this went relatively quickly since it
had been pre-planned and the bracket already fabricated.
Having the bubble off does tend to help in the process
since one can sometimes get a different access to things
near the front. Also note that the interior side panels
have not been installed at this point and this allows
extra access to wiring runs along the side areas such as
for the navigation lights.
- Basically just continuing along the wiring path but I've
been a bit delayed by personal events. With the switch
panel and solenoid board installed, I found that it was
easiest to first work with their interconects (basically
power distribution). Next up was to run ground wires to
the various areas under the seats and rearwards, followed
by power lines and interconnects. I've deferred mounting
the actual instrument panel and most of it's wiring
consists of pre-strung power / ground wires, sensor
inputs and antenna coax.

- I've also added the various firewall penetrations. Rather
than the single large grommet supplied in the kit, I've
used special pass throughs at each of the four corners
and also roughly the center bottom. This allowed me to
make the vertical wiring runs within the enclosed cabin
and makes for very neat weather resistant penetrations.
I've also added the starter and alternator cables ...
these are a bit of a pain to work with and worth the time
to figure out how to make them as short and straight a
run as possible. For now, I've run a ground cable from
the frame tab to the alternate case pad for mounting an
alternator ... this isn't the cleanest / shortest way but
there was no real convenient point on the case. It does
make it somewhat crowded with the oil lines and starter /
alternator / ground wires, but it can be done if
everything is well supported.

- I continued doing some wiring cleanup and finalized the
routing for all the wires inside the cab. I've been
delaying the marriage between the instrument panel and
the craft ... it's much easier
to work on the panel while it's still on the bench.
However, I also realized that I'm putzing over this and
not moving ahead very fast. I finally took the panel out
to the hangar as I knew I had one potential interference
and it's much easier to have the panel beside the pod in
order to check measurements. That was resolved by moving
one wire bundle ... what a pain and just proves it's best
to double check things first. I cut a couple of pieces of
foam with a U-shaped slot in them so the panel could
first be roughly positioned as I threaded the wires
through the conduit I fabricated for the bottom of the
pod. Once this was completed, the panel was rotated to ~45°
which still allows access but shortens the wire
requirements and prevents the service loop from becoming
too awkward. Now it's time to terminate all the
interconnects.

The wire looks like a bunch of spaghetti, but
they're all marked so it's just a matter of connecting
one wire at a time.
- I chose to pre-wire most of the instrument panel which
left the other end of the wires to be terminated at
various locations around the craft. However, there were a
few wires that I'd pre-wired to the switch panel which
then needed to be routed and connected to the instrument
panel. Due to space constraints, these wires were
extremely time consuming and difficult to route /
terminate, but at least that step has now been completed.
The lesson learned for this type of radio stack and pod
installation was that it would be much easier to have
fully pre-wired the instrument panel before installing it.
Of course, these wires would have been much easier to
route if I'd used a round radio / transponder or had left
more room under the radio stack.
- Most of the non-sensor wires (i.e. power, ground and
control) have been routed through the switch panel area
to their final destinations and a lot of them are now
terminated. This was time consuming to try do a neat job
of keeping the wires parallel but it does reduce the
bundle size considerably. The sensor wires should be
relatively quick to route as the runs have been
established and the firewall pass-throughs are in place.
I made a mistake of straining my back muscles while
working in the awkward pod area and then aggrevating it
as I continued doing more wiring ... this has really
slowed things down for me and it's time to take a bit of
a break from wiring while I let the muscles recover.

- Most of the sensor wires have now been run through the
switch console area. That leaves the coax and pitot /
static / MP lines to be finalized and then this area can
be buttoned up. The real time consuming part of the
wiring is just about complete.
- All of the wiring has been run to it's various locations
(excluding coax and boom) and I continued to clean up
some of the wire routing and terminating some of the
sensor wires ... will the wiring ever end? One of the
things I noted when wiring the rotor tach generator is
that it would have been more direct to run the wires to
it from below, but this would likely have caused the
wires to rub on the upper transmission casting. I
actually looped the wire up to a pylon support rod and
then back down.

The loop at the top is a bit bigger than required
since I also have a different sender (with different
connectors) that I want to test. Also note the sheet over
the fan opening ... works great to catch small dropped
pieces and to keep "junk" out of the shroud.
I also realized that it would have been a shorter and
more direct run if I'd put my bulkhead pass through for
the oil pressure transducer in the firewall side rib
instead of the bottom one. Oh well, it's now wired and no
big deal.

I also detected a potential wiring problem with my
LASAR® system as I have the version with a CHT probe in
the hottest cylinder which becomes another factor in
determining the advance. To accomodate this plus the CHT
gauge, I have a dual CHT probe i.e. one physical probe
but with two sets of wires. The problem is that the
Westach probes supplied with the CHR kit are 4' in length
while the Unison M5340-03 probe is only 3'. No big
problem *unless* the cylinder I
pre-selected as hottest (#4) turns out not to really be
the hottest and I have to switch the probes around. To
accomodate this, I've left extra length on all
the CHT extension wires so that hopefully they can reach
the Unison probe regardless of which cylinder it is
installed in.
- I kept the non-electric instruments out of the panel
while I was doing all the wiring in order to avoid
bumping them and to create better access to the wiring.
These instruments have now been installed and the pitot,
static, and manifold lines have all been run from the
instruments to their respective terminations. There is a
choice of using either Tygon tube with push on barbed
fittings or Nyla-flow/seal tube and fittings. I chose to
do all my panel routing with Tygon tubing as it made it much
easier to route the tubing out of the pod and down to the
switch panel area. The panel is now ready for electrical
checks. For now, I've
installed my modified analog tach (similar to the CHR
digital tach) but I've since recalibrated an R22 tach
that I'll be testing at some time in the future ... it's
a simple swapout due to the use of electrical connectors
and pre-wiring.

In preparation for installing the bubble, I've
also been doing a few of the miscellaneous details that
I'd deferred, such as the control cables exits from the
cabin area. Besides some of the console electrical
testing, I want to get my control rod boots installed
before installing the bubble. Although it's relatively
easy to do this afterwards, it will be much easier to
install the top one without obstacles.
- I've been a little side-tracked of late as I got involved
with a TSB investigation into a fixed-wing fatality.
Certainly this is a sobering experience and makes one
rethink every aspect of what they are doing. More
importantly, it reinforces that every nut, bolt, joint
and wire is important ... any shortcuts are just inviting
major problems. Although a particular item may not be
critical by itself, it may cause the first event in a
sequence that leads up to a much larger problem.
As far as actual work on my craft goes, I've been
finishing up various minor things that need to be done at
some point along the way. Seems I forgot to run the wires
for my map light (dumb!) and this took a lot of extra
time to do it properly after the basic wire bundle had
been routed, laced and was already in place. Other tasks
included things like the headset jacks, the ANR power
supply, the primer line routing and making sure that all
the wiring is well protected against abrasion.
One of the things I'd been waffling on was how to secure
the spark plug leads on the boom side of the engine. I've
seen pictures of several ships that used the typical
fixed-wing technique of attaching the leads to the shroud
but I really don't like the look of that and it makes one
more thing to disassemble if you're taking the shroud
sides off. I finally decided to go with clamps on the
intake runners the same way as is used on the O360-J2A in
an R22. I ordered LW18959-175-25 clamps from Progressive Air
... interesting that a Canadian distributor was cheaper
than the US online outlets. As an alternative, ECI
part # AEL71910 is a cross-reference to these.

- The bubble has now been mounted and is in it's final
position. Removing a bit of the protective covering where
it contacts the various parts was not a problem but it
was certainly a lot more difficult to remove the covering
along the narrow edge. With the "rubber"
molding in place it was more difficult to accurately
position the bubble, but eventually it was moved into the
proper position.
N.B. Installing the bubble clips was quite simple for me
but part of that can be attributed to my use of non-standard
kick panels as described in the Cabin
section. Because of that change, my kick panels were
installed after the bubble was
mounted which allowed for easy access to all
of the front bubble clips. Without this change, access
would be very difficult and other builders might want to
consider a different assembly order than I used.
The engine shroud has now had it's final tightening of
all the various screws that hold it together. This was
also the perfect time to double check that various wires
and lines had been tightened and properly clamped in
place.
In parallel with the other finishing tasks, I had already
done the final paint and cleanup on the tail boom. Once
the painting was complete I added tubeseal to it using a
funnel and a short piece of tubing. The fact that it
would only run slowly into the boom and then an air
bubble had to escape through the oil in the funnel was a
good indicator that the boom is already sealed.

The boom has been installed in order to do the
initial setting of the pillow block shims and to trim the
tail rotor driveshaft to length. The shaft will then need
to be welded shut and painted. I'm not sure if I'll
permanently attach the boom or remove it again ... I need
to talk to my hangar mates about space requirements.
- Wouldn't you know it ... just as everything is rapidly
coming together, mother nature strikes. I'm still trying
to isolate the cause, but I'm pretty sure that when I
installed the bubble and did some general cleanup that
some of the accumulated dust contained fiberglass
particles. As I was doing this work without gloves, my
hands have developed a severe itchy rash that looks like
a whole lot of mosquito bites. Normally I'm extremely
tolerant of fiberglass shards and have no known
allergies, but the result is that all work has slowed to
a snail's pace again as it is very painful to grip
anything, apply pressure or even close my fingers for
that matter ... hopefully this will cure up in a
reasonable time frame and the long term result will only
be a valuable lesson.
Update: Lesson learned the hard way to be very careful
around fiberglass sanding residue ... two weeks and my
hands are useable again but there are still some scabs
that are healing.
- The tail rotor driveshaft has been cut to length, welded
and drilled. It's now awaiting better weather so I can
apply a thin coat of paint to
it.
I've been fighting with the carburetor installation. This
was one of those things that I'd assumed was a simple
bolt-on and had delayed it's installation so as to avoid
getting dust on/in it. After resolving several mounting
issues as described in the Engine
section, I'm still wrestling with the SCEET tube routing.

Bad flash shadow on the oil pickup fitting but one
can just see the edge of the blue fitting. The tape is
holding a piece of plastic in place to temporarily seal
the intake.
- A new offset flange has been built for the carb air. I've
also solved some miscellaneous issues such as how to
mount a rear hanger for the exhaust. Construction on the
doors has also been started. While there is no rush for
these during the summer, the jig is now available and I
can work on them whenever I have a free hour or two.
Since there will be room in the hangar for quite some
time, I did the final bolting of the boom to the main
frame.
- Besides some painting, I've been doing various small
tasks such as mounting the carburetor (for the final time
I hope), routing wires on the tail boom and running some
of the oil lines. I have the original style oil tank and
one of the things I found was that the crankcase vent
hose was resting on the frame just above the tank. Since
this is the type of thing that I'm trying to resolve
before it leads to later problems, a couple of adel
clamps solved the issue.

- The tail rotor driveshaft has been painted and installed
along with the pillow blocks and couplers ... more
details in the Controls
section. This was a more time consuming process than I'd
thought but mostly due to the delays with painting and
the finnicky nature of trying to get parts to just
fit followed by their precise alignment. The tail rotor
was found to have a very stiff pitch control and I spent
the time to remove the rod ends and loosen them ... the
factory had chosen to just install them as-is even though
they couldn't be moved by finger pressure alone.
- The exhaust system has had gussets added to the tailpipe
and I think I'm finally content that it's ready for final
installation. The only question is whether I send it out
for ceramic coating. The seats are now with the
upholsterer and hopefully they'll be finished in the near
future.

- The routing of the oil lines has been finalized and the
hoses installed. I ended up changing the oil tank fitting
for the right valve cover drains (i.e. cylinder #4) to a
45° fitting as this allowed the line to run more
horizontal rather than have a dip in it that would trap
returned oil. The routing of the oil lines, fuel line,
starter cable and SCEET tubing is a bit of a Catch-22 ...
it seems that the best routing for one of these tends to
make it a bit more difficult for the next item. I'm not
sure what the best sequence would be but I did mine in
the order of: electrical, oil cooler, oil tank, fuel then
SCEET. As each line is being run one has to try envision
whether it will interfere with items that still haven't
been installed. Since the SCEET tubing is by far the
bulkiest, one has to be very
consious at all times of where it will go.

- I finished off a few miscellaneous things like wiring the
tail light and the chip detector (disconnected for break-in).
One of the concerns I had was making sure that the tail
boom was properly grounded to the main frame since the
boom supplies the ground circuit for the tail lamp and
chip detector plus acts as a ground plane for the antenna.
While the boom attachment bolts might
supply a suitable electrical connection, I chose to add a
separate bonding wire to guarantee continuity. The tail
rotor gearbox did not have a good ground path through the
paint and required either a bonding strap or paint
removal and a star washer which I chose to do. The main
rotor gearbox's chip detector appears okay since there
are a lot more attach points ... seven mounting bolts
plus four pylon bolts.

- I did the initial fitting of the tail rotor push/pull
cable and then changed the location of the firewall
penetration to get a bit more slack in the cable to allow
it to better follow the boom contour. Both the front and
rear frame tabs that hold the cable ends needed to be
bent to allow for cable alignment. The Rigging Manual
instructions did not work for my setup as the tail rotor
control arm moves considerably more than the cable (2-5/8"
versus 2-1/8") ... I'm still working with the
factory to identify a solution but
so far they haven't provided a consistent and reliable
way to rig these blades. The front end of the cable
required a cable extension as I could not get the rod end
to reach the pedals based on the location where the
factory welded on the attach bracket.
- The slot for the pitch rod (center control rod to the
swashplate) has been considerably enlarged and an extra
bubble clip fabricated. I can now get the full range of
movement required without any binding. However, the seal
that I fabricated will no longer work and I need to
fabricate a new one.

- The seats have been received back from the upholsterer. I
was waiting to cut the slots in the seat support sheeting
for the seat belt passage until the final seats were
received ... I can now go ahead with that. I'd also
delayed trimming the cyclics and fitting the grips until
the seats were available ... another task that I can now
tackle. Since the upholstery shop is on the field, they
will also be making up the various cyclic and collective
boots plus some floor carpeting. I've left this with them
as very low priority items when they need a small task to
fill in some time.

- Although my hangar mates have a lot of adel clamps, the
one size they were missing was WDG5 which I needed for
the tail rotor push/pull cable. These were ordered and
finally arrived ... the push/pull cable is now clamped in
place. Since I was working on the boom, I decided to
install the strobe wiring and head ... with that done,
the boom is now complete with the exception of the final
tail rotor blade rigging and bolting the horizontal
stabilizer in place. The stabilizer is being left off for
now to avoid hangar rash. The other thing I need to do is
find a clear adhesive similar to RTV to add some extra
support to the vertical stablilizer.

- I've attempted to re-rig the main controls again but I'm
still not happy with the result and haven't locked the
various adjustments in place. Although this sounds easy
in the manuals, it's much more difficult when you can't
achieve the results that are quoted. I've also started to
prepare my main blades ... this is also a bit annoying
and taking extra time as my older style swept tip blades
are unequal lengths.
- I decided it was time to finally cut the slots in the
seat support sheeting that allow the seat belts to come
through. In hindsight, it's a bit of a Catch-22 ... it
would have been easier to cut these slots during initial
fabrication and before paint, but until the actual seats
are available the exact position isn't known. Regardless,
it's now done and the seat support sheeting has been
installed for the final time (hopefully).
- The holes for the blade tip weight modification have been
made ... hopefully I'll be able to install the epoxy/shot
and finish this modification in the next few days.
- The blade tip weights have been added and a stripe
painted on the blades. Although I'm not ready to mount
the blades immediately, the painting of the stripe was
the reason behind doing this slightly out of order. Since
I'm using an epoxy urethane paint (i.e. a noxious hazmat)
that I didn't want to spray inside the hangar. There was
a nice weather break (unseasonably warm ... actually a
record high for that day) and I wanted to get this done
outdoors before the snow starts to fly ... mission
accomplished.

- With the seat support sheeting in place, all the seat
belts have now been installed. The carb heat control and
primer pump with internal lines have also been installed.
- I'd been delaying the final adjustment of the control
rods and a bit of the interior work until I had a
suitable exit boot for the pitch control rod. With this
boot in place, the headboard has now been installed and
final rigging of the control rods has been done as they
should not need to be removed again.

- The fuel tank installation had been delayed until after
the control rods had been rigged as it's MUCH
easier to access the swashplate without having to reach
up and over the tanks. With the control rods set, I then
installed the tanks ... it sure makes it look different.
As noted in the Engine
section, I first had to TRY get
as much of the chips and swarf out of the tanks as
possible. Once the tanks were mounted using T-bolt
straps, I then fabricated the inter-tank bracing. I'm
well aware of the controversy of rigid versus semi-rigid
mounting and I chose to make it as rigid as possible
using an X brace. I must be getting sick of painting (plus
the cold weather) as I decided to make the braces out of
1/2" stainless tube.

- The exhaust system has now been installed. There are a
lot of small items such as the mixture control cable that
I was delaying in order to make sure there was no
interference with the exhaust or even too close a
proximity. These can now go ahead. In hindsight, I wish
I'd just built a custom tuned exhaust right from the
beginning. I wasted a LOT of
time, money and frustration correcting the alignment of
the CHR exhaust and preparing it for installation. I now
believe this effort would have been much better served by
just making a performance enhancing system right from the
start.

- With the exhaust in place, I finalized the control cable
runs, oil tank vent line, cabin heat duct, carb fuel line
and plug wire routing. It seems like there is no perfect
routing for all these items and each placement interacts
with the others. I also used a fair number of adel clamps
to hold everything in place and prevent movement and
possible chafing due to vibration. I tried to keep the
fuel line from gascolator to carb as clear as possible
... although this worked out fine, I ended up adding one
adel clamp in the center due to it's length. One thing I
would recommend is to not do the final cut and
installation of the control cable ends until all
routing of these items is finalized. I know that I moved
one cable in this iterative process and it resulted in a
slightly longer (perhaps 2") run but negated an
interference issue that I had.

SCEET tube for cabin heat not installed these
pictures

A bit of electrical termination still required i.e.
landing light
- With all the various lines on the left lower side having
been routed, I added the cabin heat selector valve and
it's SCEET tubing. The valve basically hangs from the
exhaust (about 3/16" below) using a short piece of
SCEET tube but I did add a couple of stainless tangs at
the top of the selector which go inside the exhaust can.
Between the tangs and the SCEET tube, there is very
little movement of the selector valve.

- I'd been delaying the installation of the cyclic sticks
and grips until after the seats were installed as these
needed to be adjusted for height and rotation using the
final configuration. The sticks were trimmed and tested
then painted. After that, the grips and associated wiring
were installed ... I've terminated the wiring in plugs so
I can easily remove the sticks.

- I needed to finish a bit of engine wiring that was much
easier to do from underneath the craft plus I also needed
to take some pictures of the craft for the CofR
application. Soooo ... I finally took it off the casters
and put it up on it's skids. I even got to try out the
ground handling wheels (not impressed with the tires) as
I had to move the craft around for the pictures. What a
world of difference when working on it now. Although it's
now possible to work underneath the craft and it's much
easier to work on certain interior areas, it's also much
harder to work on the boom and mast areas due to their
increased height. If a builder decides to use the low
casters like I did, then my recommendation would be to
leave them on for as long as possible.

- With the extra room under the craft, I could now add the
pitot tube and the belly mounted VHF antenna. Now that
all of the sensors are finally connected, it's time to
perforn final checks on all the electrical wiring. This
is done by closing the breakers one at a time and then
testing the attached devices. The only one that really
can't be tested until engine startup is the alternator
charging. Due to it's potential of affecting a lot of
other devices, it will be tested at a later time with as
many breakers pulled as possible. First round of snags
indicated a questionable oil pressure gauge (or sensor),
a questionable CHT probe and a partial fault in my tach
backup power monitor.
- The tach backup power monitor simply required another
diode but it was a real bear to install due to it's
location. The avionics (transponder, radio and GPS/COM)
have been installed and had initial testing. Without a
tester, the transponder can't really be tested in the
hangar but it does show the correct pressure altitude
indicating that the encoder is also working. The intercom
and radios are much easier to test, especially since I
also have a handheld radio. The GPS function won't be
able to be tested until the craft is outside the hangar
... hard to see satellites through a metal roof. The one
thing this testing did identify is that the microphone on
my passenger headset has an issue that will require
servicing ... it only shows up with another headset
plugged into an intercom system. I guess that's what I
get for buying it as reconditioned. In hindsight I
realize that I'd hooked it into my handheld radio to
verify it's operation but only checked the headphone part
without thoroughly testing the mic ... lesson learned. It
looks like I either did a major wiring error on the
Westach quad gauge with oil pressure or the gauge is
faulty ... with only shunt power (amp meter) and the
breaker pulled there is still power to the rest of the
meter and the sensor. Next step is to pull the panel and
investigate the wiring and possibly remove the gauge for
servicing.
- The dust boots have been installed on the cyclics and
collectives and this meant that the bolts in the cyclic
could have their final tightening. I'm really not
impressed with the design of the cyclic fore-aft pivot
... this hole was drilled oversize at the factory which
introduces slop into the stick. If one tries to tighten
the pivot bolt to reduce this effect then it introduces
friction into the stick. Not a good design and one of the
long-term modifications will be to change this pivot to
some kind of bearings. The dust boot on the pilot's
collective presented a problem in that I'd welded a tab
in place for the collective friction and hadn't left a
lot of room for a dust boot. This meant that the boot had
to be extremely short (less than 3"). While it works
(barely), I'm thinking that I'm also going to have to
move the collective friction attach point forward to gain
more clearance.

- The headset and gauge have been sent to their respective
manufacturers for servicing ... hopefully there will be
reasonable turnaround on them. The carpets have been
completed and installed along with a few other small
details like mounting the fire extinguisher. A few other
items like the custom light dimmer box have been
fabricated.

- An awful lot of small details have been completed. The
gauge has been received back from Westach (repaired as
warranty even though long since expired) and the panel
was re-assembled. The throttle grips have been assembled
as has the control box on the pilot's side. The ELT
antenna was mounted as was the transmission filler / vent.
The main blades have had their initial mounting but will
be pulled in order to complete some work on them. The
fuel level senders were calibrated as was the oil tank
which was filled and calibrated. The empty CofG was
located and the craft weighed. Other small things were
attended to in order to get the final inspection
performed.

- The final inspection was performed (snag fee) and I
received a Flight Authority. The main blades were trimmed
to similar shapes, had trim tabs added, were statically
balanced and were finally mounted. The tail rotor had
it's throw increased to the maximum that we could get and
was then dynamically balanced, followed by a dynamic
balance of the main blades. Finally it was time for first
hover! It's alive!!! At this time I guess it's no longer
final assembly (other than doors) but has moved into the
arena of maintenance.

- The doors have been fabricated and
installed but the vents have not been installed in this
picture. Basically that's it for major fabrication. I
still need to paint my seat bins and I'm going to add an
exhaust deflector but those are minor items that fall
more into the maintenance arena.

- The craft has now been both
trailered and flown with the doors on. I need to do some
more work on cooling and also the track & balance but
those are rigging and maintenance issues.

MISCELLANEOUS
During construction I had been very careful that all the
various holes were drilled to exactly the right size; 8-32 screws
were a #19 drill, AN3 bolts were 3/16", AN4 bolts were 1/4"
drill, etc. For large pieces that are installed with floating
nutplates, I made sure that at least one of the nutplates had a
precise screw hole such that it would preserve the alignment
while the other floating nutplate holes were of the larger
variety that allow for some movement of the parts. This
philosophy worked well on all the various aluminum panels but it
does cause a potential problem on some of the thicker steel parts
... if anything more than the thinnest coat of primer enters the
hole, then it needs to be re-drilled after painting for proper
screw/bolt clearance. This drilling process can then remove the
protective primer and paint and create a place for corrosion to
start. While this close tolerance is acceptable for critical
holes that align the running gear (especially if Corrosion-X or
something similar is used), it can easily be prevented in non-critical
areas by just using a slightly large
drill before painting. Also note that the more pieces I assemble,
the more I feel that critical holes should be under-drilled and
then reamed to size.
I worked with an AME (Canadian A&P) who always dipped all
bolts and nuts in Corrosion-X before installation. His reasoning
was that any slight scraping of the cadmium coating is a
potential point of corrosion and this would help prevent it. I'm
also putting a bit of Corrosion-X on each of the floating
nutplates and also into any of the holes that had to be re-drilled
after painting.
I have found one aspect of standard AN bolts that I really
don't like; it would appear that their length specifications are
designed for a tension installation of thicker material and not a
shear application. Specifically, there are many places where I
feel that a bolt one size shorter could be used which can be done
with two thin washers or one regular (thick) washer, rather than
three thick washers, and still provide the proper threads for a
cotter-pinned castle nut. However, if one carefully looks at this
they can see that the threaded side of the bolt actually has the
taper and/or threads within the
material's hole and this allows some extra play, even on 1/8"
material. Several dozen bolts that are 1/8" longer than
required and each having two extra washers does add up in weight
and extra parts. However, with the compromised fit one has to go
with the longer bolt.
The AN960 washers we use are actually stamped from a piece of
sheet metal and have one side with rounded edges and one with
square edges and a rougher surface. I'd always thought that if I
put the rounded side towards the work piece then I'd prevent
scoring the surface or cutting through any coating. I recently
read an article that made me realize that while the above may be
true, that orientation is backwards of what it really should be.
If the squared edge is towards the work piece then the rounded
edge is towards the nut and it will allow the nut to rotate
smoothly and result in a more consistent and reliable torque
setting.
The primary fastener nuts supplied in the Safari kit are AN310
castle nuts and AN365 elastic stop nuts. Most locations should be
able to use the slightly lighter AN320 shear nuts instead of AN310's
if the builder so desired. I've used MS21042 all metal stop nuts
in many places ... they're very light and convenient for places
like adel clamps. These nuts are extremely effective and it
should be noted that they are the predominant nuts used by
Robinson. Also, these nuts can be used in higher temperature
areas around the engine whereas it is accepted aircraft practice
to not use elastic stop nuts forward of
the firewall or in any area subjected to heat.
After going through all the trouble of trying to get a good
paint job, I find it ironic that many people then just tighten
screws against the new paint thus gouging the paint and going
down to bare metal. The simple solution is to use a thin nylon or
fiber washer under the screw head. These are available quite
cheaply at most of the large electronics distributors and I've
noticed that Aircraft Spruce also carries them as part # 04-00217.
I've also found that the nylon washers seem to add a bit to the
gripping power of the screw ... I assume this is due to
compression of the nylon.
One builder was having trouble getting the protective coating
off the bubble. Although part of it came off quite cleanly, there
was a large amount that only seemed to come off when using his
finger nail and wouldn't "peel". After deferring this,
the next time he tried removing it, it peeled quite easily. The
difference was ambient temperature ... in the 90's for the first
try and in the 70's during the second try. I had no problems
removing it in mid 70's temperature even though it had been in
place for many years.
<NEXT> Rigging
<BACK> Preparation and Paint
<PAINTING> Novice
Painting Thoughts
<HOME>
Last updated: September 18, 2009